Timeline

 

Our Verona Building Timeline

Date Event Description Completed
8/19/2012
Contract Date Signed the Contract to build a Verona on cul-de-sac lot.
8/23/2012
NVR Signing Had to sign the numerous documents and provide bank statements for the loan approval process.
9/8/2012
Final Changes All of our ‘final’ changes had to be submitted and approved
9/8/2012
Guardian Met with Guardian to discuss options. Left with standard options plus an extra TV for Morning Room. Asked for pricing on a few other things
9/13/2012
Guardian Final Joe from Guardian met me at work to sign the final changes to the Guardian Order. Added whole home pre-wire.
9/17/2012
NVR Loan Loan was officially approved.
9/24/2012
Pre-Construction Mtg Met with Salesperson and Project Manager to go over all options and discuss the projected dates.
9/24/2012
Lot Staked Lot was staked so we could see how the house would sit on the lot. Requested a move of window from Living room to Study on side of house.
10/03/2012
Dig Day Lot was dug and Main sewer drain was connected to the basement utility area.
10/04/2012
Footers Footers for the foundation were poured
10/05/2012
Storm Drain Plumbing for storm drains around the house has began.
10/08/2012
Foundation Foundation wall frames were installed and foundation was poured.
10/09/2012
Foundation Foundation frames were removed and the basement starts taking shape.
10/10/2012
Drainage Waterproofing for the walls was installed around the exterior walls of the foundation.
10/11/2012
Drainage Downspouts were connected and installed around the foundation.
10/15/2012
Foundation The foundation was backfilled. Large stone was also added to the driveway. Basement was filled with small rock and leveled.
10/17/2012
Lumber All of the lumber and steel support beams were delivered.
10/22/2012
Framing First floor framing was started.
10/23/2012
Framing The remainder of the first floor was framed, second floor subflooring was laid.
10/24/2012
Framing More progress on Second floor framing
10/25/2012
Framing Roof sheeting installed to give the completed framing look.
11/12/2012
Closing Our official closing date has been determined and notification sent.
11/12/2012
Framing The incorrect roof pitch on the 3rd car garage was corrected.
11/12/2012
Pre-Drywall Met with the PM and went through the pre-drywall meeting to make sure all outlets and plumbing was correct.
11/15/2012
Drywall First floor drywall was hung
11/16/2012
Garage Door Garage doors were installed.
12/01/2012
Kitchen Kitchen cabinets and countertops installed.
12/01/2012
Fireplace Fireplace stonework completed. Some issues to be fixed later.
12/06/2012
Electrical Electrical was approved so all light fixtures have been installed and are now working. No more flashlight visits 🙂
12/14/2012
Carpet Subfloors have been leveled and sanded and carpets installed.
12/17/2012
Final touch-up Final touch-ups have began.

 

 